Steps for installing NAC 3000R?
1.
Administrator
receives the unit from BioEnable technologies.
2.
He/She
unpacks the unit.
3.
Goes
through the checklist of entities to be present.
4.
If
the number of items mentioned in the checklist correspond with the items packed
then proceed to next step.(if not)
5.
The
administrator has to ensure that no physical damage has been sustained by the
unit during packaging and forwarding.(if Yes)
6.
The
administrator then goes through the complete hardware installation manual.
7.
The
very first pre-requisite is availability of AC power source as per the
specifications provided in the hardware installation guide.
8.
Please
ensure proper Earthing and other electrical considerations.
9.
Take
a close look at the direction in which the power connector has to be connected.
10.
Plug
in the power connector after ensuring the above steps.
11.
The
default initialization screen should appear.
12.
After
the initialization the display should remain stable and the default “Welcome”
screen should be seen
Last modified 2008-01-17 18:17